Kramat Jati Blue Taskforce Personnel Construct Water Channel in Cililitan

As many as seven personnel of Kramat Jati District's Blue Taskforce, East Jakarta construct new water channel at RT 01/04, Cililitan Urban Village.

targeted to complete in two weeks

Kramat Jati District's Water Resources Unit Head, Muchlis said the 40 meter-long water channel constructed was started on August 13, 2025.

"The work is run manually and is targeted to complete in two weeks," he said, Friday (8/15).

Karet Pasar Baru Timur V Water Channel Dredging Completed

He explained that the channel is made with 40 cm of depth. Hopefully the channel will be able to eliminate inundation during heavy rain.

"I also ask the residents to help maintain the cleanliness of the drains, especially by not throwing rubbish carelessly," he added.

Meanwhile, one of local residents, Dody (45), admitted the channel construction was requested at Musrenbang.

"There was no water channel here, so we proposed it. Thanks to the Water Resources Unit for responding our request," he admitted.

Linked News
Popular News indeks
  1. Abdul Muis Building Fire Response Nears Completion, No Fatalities Reported

    access_time08-08-2026 remove_red_eye584 personAldi Geri Lumban Tobing
  2. Jakarta Ensures Public Services Stay Operational After Abdul Muis Building Fire

    access_time08-08-2026 remove_red_eye548 personFakhrizal Fakhri
  3. Pramono Urges MUI to Strengthen Synergy in Maintaining Jakarta’s Harmony

    access_time12-08-2026 remove_red_eye537 personDessy Suciati
  4. Jakarta Remains Indonesia's Top Investment Destination

    access_time07-08-2026 remove_red_eye519 personAldi Geri Lumban Tobing
  5. Thousand Islands Conducts Vehicle Emission Tests on Three Islands

    access_time07-08-2026 remove_red_eye514 personAnita Karyati